SEPPES PROJECT / FOOD-PACKAGING MANUFACTURING

Mixed Industrial Door Systems for a Food-Packaging Factory

A packaging manufacturer needed different door arrangements for external loading openings, internal production passages and a crane-served route. SEPPES coordinated sectional doors, high-speed curtains and a special inverted arrangement around the new and existing buildings.

External and internal openingsCrane-clearance coordinationPhased factory upgrades
White sectional door at a concrete opening in a packaging factory
Sectional door at a packaging-factory opening during building work.
Initial package
6 sectional + 3 rapid doors
Building layout
New and existing workshops
Key interface
Overhead crane route
Initial handover
August 2024
THE PROJECT

Choose each door around the work performed at its opening.

The project illustrates how a door schedule can connect product selection, building levels and handling equipment across a mixed factory layout.

A Factory with Different Opening Duties

The site combined a new multi-storey production building with improvements to existing workshops. The factory manufactured packaging containers and used printing and forming processes, with material movement between production areas and external loading points.

  • External openings for loading and material handling.
  • Internal passages requiring frequent access and separation.
  • A route whose overhead crane movement conflicted with a conventional door-head arrangement.

A Coordinated Door Schedule

SEPPES reviewed the openings individually rather than applying one door type everywhere. The initial handed-over package contained six sectional doors and three rapid doors.

  • Insulated sectional panels for the selected external openings.
  • Yellow flexible curtains and viewing sections for production passages.
  • A specially arranged rapid door to coordinate with the crane route.
OPENING-BY-OPENING SELECTION

Different routes called for different arrangements.

Opening dutyProject arrangementInput to confirm on another site
External and loading openingsSectional doors, including 4,000 × 5,000 mm openings and a 3,000 × 3,600 mm material opening.Opening labels, floor levels, external exposure and the equipment using each route.
Existing-building accessA 4,000 × 4,000 mm sectional opening and rapid-door arrangements were included in the wider scope.The existing structure, services, removal work and usable clearances.
Internal production passagesYellow rapid curtains with transparent viewing sections and brush seals; sizes varied by opening.Traffic, visibility, separation needs and the surfaces available for fixing.
Crane-served routeAn inverted rapid-door arrangement was designed to avoid the overhead handling path.The full crane and load movement envelope and a configuration-specific installation drawing.
Controls and later interfacesAccess-control functions and terminals reserved for later automated transport.Which connections are required now, which are reserved and who owns future integration.
COORDINATING THE CRANE ROUTE

Put the lifting envelope on the same drawing as the door.

The crane-related door was a project-specific solution. The useful lesson is early coordination between the building, lifting equipment and door teams.

Resolve the Physical Conflict First

At one route, a conventional roll and drive position would conflict with overhead handling. The project used a special inverted arrangement after reviewing the opening and the crane’s working area.

For a similar opening, provide the complete lifting path, the load envelope and the positions used for inspection and servicing. A door opening size alone will not show whether the moving equipment and door assembly can coexist.

Keep the Configuration Specific

The location of the roll, drive, guides and protective components must be considered as a complete arrangement. The special layout in this project is a reason to request an engineering review, rather than a general instruction to reverse a standard door.

Agree the approved drawing and the responsible parties before manufacture. Include installation access and the safe sequence for putting the combined route into service.

STAGED IMPLEMENTATION

Work from a labelled opening schedule.

  1. Survey the New and Existing Buildings

    The team checked opening dimensions, levels, headroom and mounting interfaces across the different workshop areas.

  2. Agree the Door Types and Interfaces

    Sectional and rapid-door arrangements were allocated to the relevant openings, with special attention to the crane-related layout.

  3. Coordinate Site Access

    Installation work was coordinated with lifting and access equipment and the readiness of the building interfaces.

  4. Commission the Initial Package

    The first three rapid doors and six sectional doors were installed, checked and handed over in August 2024. Further factory orders followed.

WHAT THE PROJECT DELIVERED

One coordination process, several opening solutions.

The project also included a separate fire-compartment door scope. Any fire-rated assembly and alarm interface require their own approved specification and acceptance process; the rapid-door arrangements described here do not establish fire resistance.

A Practical Product Mix

The external and internal routes received different door arrangements suited to their roles in the factory. The initial package combined nine doors, while the opening schedule supported later additions.

Handling Equipment Included in the Review

The crane-served opening was treated as an interface to be resolved before installation. Door position, structural clearances and handling movement were reviewed together instead of being left to separate trades on site.

PLAN YOUR PROJECT

Build a door schedule the whole project team can use.

Schedule fieldInclude these detailsUse in the proposal
Opening ID and dutyFloor, internal or external route, traffic and material-transfer role.Allocate the door family and track or curtain arrangement.
Structure and interfacesWall construction, beams, headroom, fixing members and nearby services.Set out mounting, installation access and clearance responsibilities.
Other equipmentCrane paths, loads, conveyors, lifts and planned automated vehicles.Resolve physical conflicts and separate current interfaces from future provisions.
Phasing and handoverSite-readiness dates, access windows, operating checks and document requirements.Sequence manufacture, installation and acceptance by opening group.
COMMON BUYER QUESTIONS

Clarify the scope of a mixed-door package.

Why use both sectional and rapid doors in the same factory?

Different openings perform different jobs. External loading routes, internal passages and equipment interfaces should be reviewed against their own traffic, exposure and space requirements.

Can an inverted rapid-door arrangement be specified from a photograph?

A photograph can start the review, but it does not define the complete installation. Provide dimensions, the equipment movement envelope, structural details and access requirements for an approved drawing.

Were automated vehicles commissioned in the initial package?

The scope described here included connection provisions for later automated transport. A reserved terminal does not establish a completed vehicle-to-door operating sequence.

What helps compare quotations for a multi-opening project?

Use the same labelled schedule for every proposal. Include product duty, dimensions, fixing scope, controls, installation responsibilities and acceptance documents so the offers cover comparable work.

DISCUSS YOUR REQUIREMENTS

Coordinating several door types across one factory?

Share the opening photographs, dimensions, operating duty and site constraints. SEPPES can help review the equipment configuration, supporting interfaces and scope of supply and installation.