SEPPES PROJECT / AUTOMOTIVE COMPONENT MANUFACTURING

Two-Door Interlocking with Rigid Spiral Doors

An automotive-component production passage needed two rigid doors operating as a coordinated airlock. SEPPES supplied 1,500 × 2,200 mm spiral doors, helped define the supporting frames and commissioned the electrical interlock between the two openings.

Two-door airlockRigid insulated panelsPrepared steel-frame interfaces
Rigid spiral door open at a framed clean-production passage
Rigid door, prepared frame and wall-mounted controls at the production passage.
Door package
2 rigid spiral doors
Clear openings
1,500 × 2,200 mm
Control relationship
One open / one held closed
인계
May 2026
THE PROJECT

Turn an open production route into a coordinated passage.

The door package addressed the access sequence and the physical installation. Environmental performance also depends on the surrounding partition, ventilation and facility design.

The Passage Requirement

The project was part of an automotive-component production area. An open route needed a new partition and doors to organise access between the surrounding workshop and the controlled-production passage.

  • Two openings arranged along the passage.
  • Frequent access with rigid-panel door construction.
  • A normal sequence that prevented both doors opening together.

The SEPPES Scope

SEPPES supplied two silver-grey rigid spiral doors and coordinated their mechanical and control interfaces with the contractor.

  • 1,500 mm clear width and 2,200 mm clear height at each opening.
  • Details for the steel support frames and panel-wall junctions.
  • Electrical interlock connections and on-site functional checks.
PROJECT CONFIGURATION

Combine rigid doors with a defined operating relationship.

InterfaceProject arrangementQuestions for another passage
Door constructionRigid insulated aluminium panels in a spiral-track arrangement.What panel, sealing and installation characteristics are required at this opening?
Clear opening1,500 × 2,200 mm at both doors.Will the largest loaded trolley, equipment or intended traffic pass with the required clearance?
Supporting framePrepared steelwork coordinated before installation.Who designs, supplies and accepts the supports and frame-to-wall junctions?
작동Wall-mounted operating buttons.Where should users wait and request access without obstructing another movement?
InterlockA door opening held the other door closed during normal operation.Which position signals and permissions establish the sequence, and who validates it?
HOW THE AIRLOCK OPERATES

One open door holds the other closed.

The project used a two-door electrical interlock. The simple state example below describes the normal sequence; it does not define every exceptional operating condition.

Door AOpen
Door BHeld closed
Normal-operation example. The relationship reverses when Door B receives permission to open.

Define Permission and Position

The two door controllers were connected to establish the required opening relationship. For another project, write the sequence in terms of valid closed-position feedback, permission to open and what happens to a waiting request.

Identify who owns the control logic and who provides each connection. A sequence narrative and signal list help the commissioning team test the complete passage rather than checking each door in isolation.

Agree Exceptional Conditions

Power interruption, lost feedback, a blocked doorway and emergency access need an agreed response. Ask the facility and controls teams to decide those responses before commissioning.

The interlock is an operating function. It should be coordinated with the facility’s protective and access arrangements and cannot substitute for testing the complete environmental enclosure.

INSTALLATION AND COMMISSIONING

Prepare the support structure before the doors arrive.

  1. Review the Passage Layout

    The teams agreed the two opening sizes and rigid-door arrangement for the new production passage.

  2. Prepare the Frames

    SEPPES provided installation details so the contractor could prepare the supporting steelwork and coordinate it with the wall panels.

  3. Fit the Door Assemblies

    The doors were mounted at the prepared frames and their tracks and operating controls were set out for the passage.

  4. Connect and Check the Sequence

    The electrical relationship between the two controllers was commissioned and the package was handed over in May 2026.

WHAT THE PROJECT DELIVERED

A coordinated pair of doors at prepared openings.

A similar airlock needs its own pressure, cleanliness, traffic and acceptance brief. This project is a configuration example rather than evidence of a room classification or leakage value.

Mechanical Fit

The support-frame information was agreed before installation, allowing the door mounting and panel-wall interfaces to be reviewed as one physical arrangement.

A Passage-Level Operating Check

The final scope included checks of the two-door relationship as well as the individual door movements. The delivered function was a coordinated normal opening sequence across the passage.

PLAN YOUR PROJECT

Draw the passage and write its operating sequence.

Brief itemWhat to sendWhat to agree
Passage layoutLabel doors A and B, connected rooms, traffic direction and waiting areas.Clear opening dimensions and the normal access sequence.
Building interfacesWall panels, fixing members, headroom and available side space.Frame design, sealing junctions and maintenance access.
Control informationActivation points, position feedback, required permissions and existing systems.Signal ownership, connection scope and exceptional responses.
Acceptance requirementsDoor checks, facility environmental criteria and required documentation.Separate door commissioning from any wider room qualification.
COMMON BUYER QUESTIONS

Specify the passage as a system.

Does a two-door interlock establish a cleanroom class?

No. It organises the door-opening relationship. Room cleanliness and pressure performance depend on the complete facility and its qualification.

Why were steel frames prepared before installation?

The original route needed new mounting interfaces. Preparing the frames from agreed details helped coordinate the rigid doors with the surrounding partition.

Can the door sizes be copied to another passage?

Use the actual people, trolley, equipment and load dimensions at the new site. The 1,500 × 2,200 mm size describes this project only.

What should be included in an interlock test?

Agree the test plan with the responsible teams. Cover normal requests at both doors, waiting-door behaviour and approved responses to unavailable signals and other exceptional conditions.

DISCUSS YOUR REQUIREMENTS

Planning a coordinated two-door production passage?

Share the opening photographs, dimensions, operating duty and site constraints. SEPPES can help review the equipment configuration, supporting interfaces and scope of supply and installation.