SEPPES PROJECT / PULP AND PAPER MANUFACTURING

Horizontal Rapid Doors for Pulp Mill Lifting Openings

A pulp mill moved material vertically through floor openings. Humidity, process vapour and wash water complicated the horizontal door installation, particularly around the guides. SEPPES specified a six-door package with horizontal travel, stainless-steel components and raised mounting bases coordinated with the civil team. The first batch was installed and checked on site.

Horizontal door travelRaised mounting basesFirst-batch checks
Metal-slatted rapid door mounted horizontally across a floor opening surrounded by yellow guardrails
A horizontal door at a pulp-mill lifting opening during site work, with separate perimeter guardrails visible around the opening.
Project scope
6 custom assemblies
Travel plane
Horizontal, at floor level
Guide mounting
Raised concrete bases
Recorded site stage
First-batch operating checks
THE PROJECT

Floor-level guides had to work around wash water and lifting activity.

The process opening

Pulp was lifted between levels through openings in the structure. The floor and surrounding plant were exposed to moisture and periodic cleaning. The earlier arrangement put the guides close to floor run-off, which the project account describes as a source of contamination in the guides.

The door and building interface

The new assemblies travelled horizontally over the openings. SEPPES coordinated the guide levels and raised concrete mounting bases with the civil team. The project specification called for stainless-steel components around the guide and head assembly.

PROJECT CONFIGURATION

Treat the mounting base as part of the door interface.

Design itemProject configurationWhat to confirm at your site
Horizontal assemblyRigid slats travelled across the floor opening on horizontal guides.Show the lifting path, the equipment envelope, door travel and where components can be serviced.
Material selectionThe project specification called for 304 stainless steel at the enclosure, guide structure and associated hardware.Share wash-down exposure, expected chemicals, humidity and the maintenance conditions for the offered materials.
Civil interfaceThe civil team was given raised-base details, with a nominal 150–200 mm provision recorded for this project.Coordinate base levels, drainage and fixing details from the approved site drawing.
Opening protectionSeparate perimeter guardrails are visible in the site photograph.Have the responsible project team specify guarding, access controls and any required evidence for the floor opening.
Operating scopeThe source describes trial operation of the first installed assemblies.Define installation, testing and acceptance milestones for each batch of a comparable package.
ENGINEERING DECISIONS

Coordinate the lifting envelope, cleaning and maintenance access.

Resolve guide location and water paths together

A horizontal guide sits in a different exposure zone from the upright guide of a standard doorway. Review where run-off travels during cleaning, where debris collects and how the guide will be inspected. The raised mounting details in this case were developed alongside civil works for the actual openings.

Give the opening its own structural and access brief

Identify who controls access at each floor, the lifting and load movement envelope and what protection is required when the opening is exposed. Any structural, load or fall-protection duty requires its own approval and supporting engineering information for the specific installation.

Close view of a horizontal metal door with guide rails and a rectangular head enclosure
Close view of the horizontal guide rails, slats and head enclosure from the same pulp-mill project.
DELIVERY AND HANDOVER

Work from surveyed levels and record checks by batch.

  1. Survey the lifting route

    Review the floor openings, lifting equipment, surrounding structure and areas exposed to wash water.

  2. Coordinate the civil details

    The team provided the raised-base and mounting details so guide positioning could be planned with construction.

  3. Set the first guides and fit the assemblies

    The source records initial site installation, alignment and assembly of the first batch.

  4. Check initial operation

    The project record describes horizontal movement checks on the initial installations while the wider acceptance process was progressing.

PROJECT OUTCOME

What the project delivered

The first batch reached operating checks while work continued on the wider project. The site photographs show how the horizontal door, guides and separate perimeter guardrails fit around the lifting opening.

PLAN YOUR PROJECT

What to include in an enquiry

Lifting movement

Plans and sections showing the load, headroom, lifting route and clearances at each level.

Opening and adjacent structure

Surveyed levels, fixing surfaces, base design, access arrangements and guarding responsibilities.

Cleaning and exposure

Run-off paths, cleaning routines, chemicals, humidity and guide-cleaning access.

Testing and scope

Approved drawings, lifting interfaces, protective requirements, responsibilities and batch handover stages.

COMMON BUYER QUESTIONS

Questions about this configuration

Why was the door installed horizontally?

The process opening was in a floor, so the door had to travel across its plane. A normal vertical doorway would serve a different layout.

Why was the guide mounted on a raised base?

The project was designed to keep the guide installation away from direct floor run-off. The required height and drainage detail should be taken from the approved drawing for the site.

What does the photograph show?

It shows the horizontal slatted assembly, guide position and separate guardrails while work was still in progress.

How should opening protection be specified?

Provide the intended access, lifting and protection requirements to the responsible engineering team. Request project-specific technical verification for any claimed structural or fall-protection duty.

DISCUSS YOUR REQUIREMENTS

Coordinating a custom door around a vertical lifting opening?

Send a marked layout, opening dimensions, site photographs and your main operating requirement. SEPPES can review the door, mounting conditions and equipment interfaces with your project team.