Two rapid doors served material transfer into a robotic workcell. The adjacent fencing could not carry the door assemblies, so SEPPES provided independent braced steel supports and coordinated a remote control location and AGV interface. Installation and joint integration checks took place at the assembly site in China.


- Door package
- 2 fabric rapid doors
- Project opening
- 3,000 × 2,100 mm
- Cable routes
- 10–15 m project provision
- Project photograph
- Assembly site in China
The door needed its own support and a defined operating interface.
The workcell problem
Automated guided vehicles used the openings to supply and remove material. The fence defined the cell perimeter, while the door and drive needed a structurally appropriate mounting arrangement. Space near the guides also influenced where the control boxes could be mounted.
The SEPPES scope
The package used two rapid doors and custom rear-braced steel frames. Cable extensions allowed the controls to sit at the agreed remote locations. The door supplier and automation team coordinated the ordinary machine signals and took part in integration checks in China.
Plan the mechanical and control interfaces in the same review.
| Design item | Project configuration | What to confirm at your site |
|---|---|---|
| Opening and curtain | Two 3,000 × 2,100 mm fabric rapid doors with yellow curtains and brush seals. | Confirm loaded AGV dimensions, approach angles and the clearance needed when the door is fully open. |
| Support | An independent frame with rear bracing carried each door assembly. | Identify anchor surfaces, brace positions and the team responsible for support design and review. |
| Control location | The project specified extended motor and sensor cable routes of approximately 10–15 m. | Confirm routes, service access, cable requirements and termination locations with both suppliers. |
| Automation interface | The project specified Modbus TCP and agreed command and fault-feedback interfaces with the integrator. | Document signal ownership, normal requests, door status and permitted responses when signals are unavailable. |
| Reassembly provision | Threaded fixing points were specified with later dismantling and reassembly in mind. | Agree assembly references, approved fasteners, installation records and who checks the equipment after relocation. |
Coordinate the door travel and the workcell operating sequence.
Keep the load path off the fence
A cell fence can divide working zones without being designed to carry a door head, drive and guides. The support in this project was designed as a separate frame. Review brace positions against the AGV envelope, adjacent equipment and the room needed for fixing and maintenance.
Agree responsibilities at the equipment boundary
Confirm when the AGV or central controller makes a request, which status the door sends back and which party owns permission to proceed. Have the responsible integrator assess and validate the protective functions separately within the complete machinery arrangement.
Validate the interface at the assembly site.
Review the workstation layout
The team identified the vehicle route and the space available for the mounting frame, controls and cable paths.
Build the agreed package
SEPPES matched the 3,000 × 2,100 mm door assemblies and braced supports to the layout.
Install and connect at the assembly site
The team fitted both doors, ran the extended cable routes and connected the agreed control interfaces.
Run the joint checks
The team checked operation with the AGV system before the planned dismantling and overseas reassembly.
What the project delivered
The project records a two-door package with installed, braced supports and AGV integration checks at the initial assembly site. The appropriate record for later operation is the acceptance documentation for the final installation.
What to include in an enquiry
Traffic route
AGV footprint, maximum loaded envelope, route drawing and waiting positions.
Mounting and service
Support geometry, permitted anchor points, floor features, brace clearances and access for maintenance.
Controls brief
Equipment owners, normal operating narrative, connection locations and command or status data to exchange.
Acceptance scope
Assembly-stage and final-site responsibilities, required protective-function evidence and witness plan.
Questions about this configuration
Why use independent supports?
The adjacent fencing could not take the door loads. The separate braced support provided a mounting arrangement while keeping the layout compatible with the workcell.
Can the remote controls be placed anywhere?
Agree the actual cable route, control access and equipment requirements. The 10–15 m provision describes this project’s arrangement.
How does the AGV know it may approach the opening?
Define the agreed request, status and permission relationships in the equipment operating brief. Confirm system-level protective functions with the responsible integrator.
Where was the photograph taken?
It shows the doors during initial workcell assembly and checks in China.