SEPPES PROJECT / ROBOTIC WORKCELL INTEGRATION

Rapid Doors for an AGV-Served Robotic Workcell

Two rapid doors served material transfer into a robotic workcell. The adjacent fencing could not carry the door assemblies, so SEPPES provided independent braced steel supports and coordinated a remote control location and AGV interface. Installation and joint integration checks took place at the assembly site in China.

Independent braced supportsRemote control locationAGV interface checks
Two rapid doors at a robotic cell with a closed yellow curtain and diagonal frame bracing beside the open passage
The two rapid doors during domestic assembly and checks. The open bay shows a diagonal member of the independent support frame.
Door package
2 fabric rapid doors
Project opening
3,000 × 2,100 mm
Cable routes
10–15 m project provision
Project photograph
Assembly site in China
THE PROJECT

The door needed its own support and a defined operating interface.

The workcell problem

Automated guided vehicles used the openings to supply and remove material. The fence defined the cell perimeter, while the door and drive needed a structurally appropriate mounting arrangement. Space near the guides also influenced where the control boxes could be mounted.

The SEPPES scope

The package used two rapid doors and custom rear-braced steel frames. Cable extensions allowed the controls to sit at the agreed remote locations. The door supplier and automation team coordinated the ordinary machine signals and took part in integration checks in China.

PROJECT CONFIGURATION

Plan the mechanical and control interfaces in the same review.

Design itemProject configurationWhat to confirm at your site
Opening and curtainTwo 3,000 × 2,100 mm fabric rapid doors with yellow curtains and brush seals.Confirm loaded AGV dimensions, approach angles and the clearance needed when the door is fully open.
SupportAn independent frame with rear bracing carried each door assembly.Identify anchor surfaces, brace positions and the team responsible for support design and review.
Control locationThe project specified extended motor and sensor cable routes of approximately 10–15 m.Confirm routes, service access, cable requirements and termination locations with both suppliers.
Automation interfaceThe project specified Modbus TCP and agreed command and fault-feedback interfaces with the integrator.Document signal ownership, normal requests, door status and permitted responses when signals are unavailable.
Reassembly provisionThreaded fixing points were specified with later dismantling and reassembly in mind.Agree assembly references, approved fasteners, installation records and who checks the equipment after relocation.
ENGINEERING DECISIONS

Coordinate the door travel and the workcell operating sequence.

Keep the load path off the fence

A cell fence can divide working zones without being designed to carry a door head, drive and guides. The support in this project was designed as a separate frame. Review brace positions against the AGV envelope, adjacent equipment and the room needed for fixing and maintenance.

Agree responsibilities at the equipment boundary

Confirm when the AGV or central controller makes a request, which status the door sends back and which party owns permission to proceed. Have the responsible integrator assess and validate the protective functions separately within the complete machinery arrangement.

DELIVERY AND HANDOVER

Validate the interface at the assembly site.

  1. Review the workstation layout

    The team identified the vehicle route and the space available for the mounting frame, controls and cable paths.

  2. Build the agreed package

    SEPPES matched the 3,000 × 2,100 mm door assemblies and braced supports to the layout.

  3. Install and connect at the assembly site

    The team fitted both doors, ran the extended cable routes and connected the agreed control interfaces.

  4. Run the joint checks

    The team checked operation with the AGV system before the planned dismantling and overseas reassembly.

PROJECT OUTCOME

What the project delivered

The project records a two-door package with installed, braced supports and AGV integration checks at the initial assembly site. The appropriate record for later operation is the acceptance documentation for the final installation.

PLAN YOUR PROJECT

What to include in an enquiry

Traffic route

AGV footprint, maximum loaded envelope, route drawing and waiting positions.

Mounting and service

Support geometry, permitted anchor points, floor features, brace clearances and access for maintenance.

Controls brief

Equipment owners, normal operating narrative, connection locations and command or status data to exchange.

Acceptance scope

Assembly-stage and final-site responsibilities, required protective-function evidence and witness plan.

COMMON BUYER QUESTIONS

Questions about this configuration

Why use independent supports?

The adjacent fencing could not take the door loads. The separate braced support provided a mounting arrangement while keeping the layout compatible with the workcell.

Can the remote controls be placed anywhere?

Agree the actual cable route, control access and equipment requirements. The 10–15 m provision describes this project’s arrangement.

How does the AGV know it may approach the opening?

Define the agreed request, status and permission relationships in the equipment operating brief. Confirm system-level protective functions with the responsible integrator.

Where was the photograph taken?

It shows the doors during initial workcell assembly and checks in China.