SEPPES PROJECT / WAREHOUSE RETROFIT

استبدال الأبواب الدوارة في المستودعات بباب قطاعي

After the existing warehouse shutter was damaged in strong winds, the customer selected a sectional-door replacement. SEPPES supplied a 3,550 × 3,580 mm insulated door, installation information and remote technical support, while a local installation team carried out the site work.

Existing-opening retrofitLocal installation teamSEPPES supply and remote support
Existing roller-shutter opening with survey marks before warehouse door replacement
Pre-installation survey photograph showing the existing shutter and opening.
Door package
1 sectional door
Clear opening
3,550 × 3,580 mm
Panel thickness
40 mm
Installation scope
Local team + remote support
THE PROJECT

Review the damaged opening before selecting its replacement.

This case combines an existing-opening review with a clear supply-and-installation responsibility split. The photograph shows the opening at the survey stage before replacement.

The Existing-Site Problem

The warehouse’s previous steel roller shutter had been damaged during strong winds and could no longer provide the intended closure. The customer needed a replacement that could be fitted at the existing opening.

  • A masonry-and-concrete opening with an existing shutter shaft.
  • A requirement to review track space and usable clearance.
  • A site located far from the SEPPES factory.

The Agreed Delivery Model

The selected package was an insulated sectional door. SEPPES supplied the equipment, mechanical information and electrical drawings, with remote support for installation questions.

  • One 3,550 × 3,580 mm door with 40 mm insulated panels.
  • Perimeter seals, drive controls and the specified protective components.
  • Site installation carried out by the customer’s local installation team.
REPLACEMENT DOOR PACKAGE

Define the complete assembly and the installation scope.

Package itemSelected for this projectReview before another retrofit
Door size3,550 mm clear width × 3,580 mm clear height.Measure the finished opening and the required passage clearance after the old assembly is removed.
Panels and sealingWhite, 40 mm insulated sectional panels with perimeter seals.State exposure, temperature and required performance evidence for the offered assembly.
Mechanical arrangementTracks, counterbalance and specified protective components supplied as part of the door package.Check the supporting structure and available track space; use qualified installers for the complete assembly.
Drive and operationPowered operation with the agreed control box and manual provision for power interruption.Agree local operation, protective-device checks and the operating instructions.
Documents and supportAssembly drawings, wiring information and operating guidance, backed by remote technical responses.Name the on-site installer and define who completes installation checks and handover.
RETROFIT ASSESSMENT

A new door does not remove defects in the old opening.

Use the history of the failed closure to inform the new brief, then review the proposed assembly against the condition of the actual building.

Check the Structure and Remaining Fixings

The existing shaft, side surfaces and overhead space formed part of the survey. For a similar job, inspect the opening after removal so that hidden damage or unsuitable fixing positions can be addressed before the new assembly is mounted.

Record the substrate, nearby services and finished floor. Agree any structural repairs or additional supports with the responsible building team instead of assuming the previous shutter’s fixings are suitable.

Request Evidence for the Stated Exposure

The reason for this replacement was wind damage, but an exposure requirement should be written as a project specification and matched to the offered door and its installation. A panel thickness or a product-family name alone is not a wind-performance declaration.

Ask for configuration-specific supporting information and make clear which structural and installation conditions it relies on. This case does not provide a transferable certified wind class for another building.

SUPPLY AND INSTALLATION

Keep remote support connected to an accountable site team.

  1. Confirm the Retrofit Brief

    The team reviewed the existing warehouse opening and selected the sectional-door arrangement and size.

  2. Supply the Equipment and Information

    SEPPES manufactured and packed the door package with the installation and electrical information needed by the local team.

  3. Complete the Local Site Work

    The customer’s local installers carried out the physical installation. SEPPES answered technical questions remotely.

  4. Check Operation and Follow Up

    The door entered daily warehouse use, and the project team followed up with the customer after installation.

WHAT THE PROJECT DELIVERED

A replacement closure with a defined local support arrangement.

For another remote site, confirm whether a supply-only model is suitable for the available installation skills, acceptance requirements and future maintenance arrangements.

A Specified Replacement Package

The project replaced the damaged shutter with the selected insulated sectional-door configuration. The supplied size, sealing components and operating arrangement were defined before delivery.

A Clear Responsibility Split

SEPPES’s contribution was supply, documentation and remote technical support. Local installers performed the site installation; the case does not represent a SEPPES on-site installation service at that location.

PLAN YOUR PROJECT

Send both the opening survey and the installation plan.

Planning itemInformation to provideQuestion to resolve
Existing conditionPhotographs of damage, the internal elevation, side surfaces and overhead equipment.What must be removed, repaired or reinforced?
Required dutyExternal exposure, opening frequency, vehicles and environmental requirements.Which door configuration and evidence are required?
Local resourcesInstaller experience, lifting access, site power and the planned removal window.Can the site execute the approved installation and checks?
Responsibility and handoverSupply, site work, inspection, service contact and operating documents.Who signs off the completed installation and supports it afterwards?
COMMON BUYER QUESTIONS

Agree who does the work and who checks the result.

Did SEPPES install this door on site?

No. SEPPES supplied the door and installation information and provided remote technical support. The customer’s local installation team carried out the site work.

Can the existing roller-shutter fixings be reused?

They need to be assessed against the new assembly and the building condition. Ask the responsible installer and structural team to confirm the fixing arrangement; the previous installation is not automatic approval for reuse.

Does this project establish a wind rating for my warehouse?

No. State the exposure and required performance in the new enquiry and request the relevant evidence for the actual offered configuration and its installation conditions.

What must be ready before the replacement arrives?

Agree removal and access arrangements, any repairs, the mounting structure, electrical provision and a competent installation team. Keep the approved drawings and handover responsibilities available on site.

DISCUSS YOUR REQUIREMENTS

Replacing an existing warehouse shutter?

Share the opening photographs, dimensions, operating duty and site constraints. SEPPES can help review the equipment configuration, supporting interfaces and scope of supply and installation.