SEPPES PROJECT / DAIRY PROCESSING

Interlocking Rapid Doors for a Cold-Climate Dairy Airlock

A dairy factory needed a transfer route that could operate during winter weather while limiting direct exposure between the outdoor approach and production areas. SEPPES supplied three 3,600 × 3,600 mm rapid doors. Two formed an interlocked pair at opposite ends of a panelled transfer vestibule, with on-site operating checks during the winter handover.

Two-door airlock interlock3,600 × 3,600 mm openingsWinter site commissioning
A yellow rapid door seen through the viewing strip of a second door across a dairy plant vestibule
Two yellow rapid doors at opposite ends of the panelled dairy transfer vestibule, viewed through the nearer door’s transparent strip.
Door package
3 fabric rapid doors
Clear opening
3,600 × 3,600 mm
Airlock arrangement
Two interlocked doors
Handover
January 2026
THE PROJECT

Keep the transfer route usable in winter.

The site requirement

Materials moved through an entrance serving a dairy production facility. The route needed space for loaded handling equipment and a better-controlled transition into the production area during snow and wind. The layout also needed to work with the new panelled partition.

The SEPPES package

The package used yellow flexible curtains with continuous transparent viewing strips and radar activation. Two of the three doors were coordinated across the new vestibule. SEPPES provided the door equipment and technical support, coordinating the opening and installation interfaces with the partition contractor.

PROJECT CONFIGURATION

Plan the opening sequence and the space between the doors together.

Design itemProject configurationWhat to confirm at your site
Clear openingThree 3,600 mm wide by 3,600 mm high openings in the rapid-door package.Measure the largest loaded vehicle and allow for the aisle approach, turning and usable clearance.
Airlock length and viewsA panelled transfer vestibule between two doors, with continuous viewing strips in the curtains.Fit the waiting and stopping position inside the transfer area. Confirm visibility from both approaches.
Normal door relationshipThe interlock holds the opposite door closed while one of the pair is open.Identify which state permits the next opening and how the operator receives a waiting indication, if specified.
ActivationRadar activation was provided for travel through the route.Agree approach zones and separate ordinary opening requests from the protective devices.
Construction interfaceDoor positions and connections were coordinated with the partition team.Show floor levels, panel junctions, support members, guide fixings and cable responsibilities on the agreed layout.
ENGINEERING DECISIONS

Check what happens when the next door has to wait.

Make room for the load between the doors

A moving vehicle needs to clear the first doorway before proceeding toward the second. Mark the vehicle, load and pedestrian routes on the drawing and agree the permitted stopping position. The viewing bands in this project helped users see into the vestibule.

Define how the door and facility will be checked

The interlock controls the normal opening sequence. If the facility also has a temperature, pressure or hygiene target, define how the facility team will measure it. Door-operation checks can cover requests from both sides, the waiting door and protective device responses under the agreed site conditions.

A partly raised yellow rapid door with snow visible outside the dairy facility passage
A rapid door at the dairy site with snow visible outside during the winter handover period.
DELIVERY AND HANDOVER

Commission the doors within the completed transfer layout.

  1. Confirm the route

    The project team coordinated the three openings and the two-door relationship with the panelled vestibule layout.

  2. Deliver the doors

    The rapid-door equipment was transported to the site for installation during winter conditions.

  3. Fit and connect the two-door pair

    The door team coordinated mounting and electrical connections with the partition work.

  4. Check operation on site

    The team checked interlock response, radar activation and protective functions at the facility during the January 2026 handover.

PROJECT OUTCOME

What the project delivered

The site received three rapid doors and a coordinated transfer vestibule with two of the doors operating as an interlocked pair. Winter wind and snow at the approach informed the transfer layout. For another facility, state the required operating temperature range and any thermal or hygiene performance criteria in the enquiry.

PLAN YOUR PROJECT

What to include in an enquiry

Layout and traffic

Show the two door positions, the full transfer route, vehicle dimensions and safe waiting positions.

Environmental exposure

Provide the outdoor and indoor condition ranges, weather exposure and any wash-down or hygiene requirements.

Door sequence

Describe what should happen after a request, where sensors should operate and who approves exceptional operation.

Construction and handover

Provide the partition layout, supporting structure, cable responsibilities and the operating checks to witness.

COMMON BUYER QUESTIONS

Questions about this configuration

Were all three doors interlocked together?

The package contained three rapid doors. The documented airlock used two of them at opposite ends of the panelled transfer vestibule.

Is the vestibule the same as a freezer transition?

It served a dairy transfer route exposed to winter conditions. For a freezer transfer, specify the actual temperature difference and condensation or frost conditions, and request a configuration review for those conditions.

How should radar activation be specified?

Mark both approaches, waiting points and traffic outside the intended detection zone. Review door requests and the protective devices with the controls team.

What should the partition team provide?

Agree the opening dimensions, fixing structure, panel-to-frame junction and service routes on one coordinated drawing before installation.

DISCUSS YOUR REQUIREMENTS

Planning an interlocked transfer route at a food facility?

Send a marked layout, opening dimensions, site photographs and your main operating requirement. SEPPES can review the door, mounting conditions and equipment interfaces with your project team.