AGV and Rapid Door Communication: Signals to Agree Before Integration
An AGV needs a coordinated passage through a rapid-door opening, not simply a remote button that starts the door. The vehicle system and door controller need an agreed sequence for requesting access, confirming the opening is ready and reporting conditions that prevent passage.
For the door configuration, start with the SEPPES PVC high speed door. This article describes the information to agree with the AGV integrator; terminal names and wiring must come from the manuals for the actual controllers.


Separate an Opening Request from Permission to Travel
Describe what initiates a request and where the vehicle waits. A request being received does not, by itself, confirm that the opening is clear or that the door has reached the required position. The integrator should define how the vehicle obtains and checks permission to proceed.
Include the loaded vehicle envelope, any projecting load and the route through the opening. Agree how conflicting requests, pedestrians and other vehicles are managed before treating a door-open indication as a movement authorization.


Write a Functional Signal List
- Opening request and the condition that acknowledges it.
- Required opening-position or door-ready feedback.
- Passage complete and the conditions under which closing may begin.
- Door unavailable, fault and communication-loss indications.
- The agreed response to a cancelled request, power interruption or missing feedback.
These are functional descriptions, not a universal circuit. Confirm signal type, electrical compatibility, interface hardware and controller configuration with both equipment suppliers. Do not copy FWD or REV labels from another installation.


Agree the Complete Sequence with Both Suppliers
The door supplier, AGV supplier and site owner should use the same sequence document. Identify who controls the request, who determines the route is available, and who authorizes recovery after an interrupted cycle. Also define manual operation and how automatic service is restored.
Record acceptance scenarios and the person responsible for each part of the interface. An ordinary command or status connection does not establish the performance of the complete protective system.


Prepare the Integration Enquiry
Send the opening dimensions, AGV and loaded-pallet envelope, approach direction, traffic pattern, controller identification, available interface documents and a route layout. Include the proposed functional signal list and recovery requirements.
Use the rapid-door installation planning guide for site preparation and contact SEPPES with the integration brief for configuration review. For wider traffic planning, see the AGV and rapid-door warehouse planning article.